How NSW weighs view loss under the Land and Environment Court's four Tenacity steps, when councils want surveyor-certified height poles, and what photomontages add.

Aurum Render · · 6 min read
Height poles and view loss in NSW: what councils and the Court look at

When a new house or an addition would take part of a neighbour’s view, NSW has no single state rule for weighing the loss. Councils and the Land and Environment Court turn to the planning principle the Court set out in Tenacity Consulting v Warringah Council in 2004, and some councils ask for height poles so the loss can be seen on site rather than argued over from plans.

This guide sets out the four Tenacity steps, how height poles are put up and certified, and what a photomontage adds, from the Court’s and councils’ own documents, read in October 2026. It isn’t legal advice: read your council’s development control plan and ask at pre-lodgement.

The four Tenacity steps at a glance

The Land and Environment Court's four-step view sharing assessment (Tenacity, 2004)
What is assessedWhat counts for moreThe question it answers
1. ViewsAssessed: The views to be affectedCounts for more: Water views over land views; iconic views, such as the Opera House, the Harbour Bridge or North Head; whole views, where the edge between land and water is visible, over partial onesQuestion: What is visible now, and what would the proposal cover?
2. Where fromAssessed: The part of the property the views are seen fromCounts for more: Views from the front and rear over views across side boundaries; standing views over sitting viewsQuestion: From which rooms, and in which position, is the view enjoyed?
3. ExtentAssessed: The extent of the impact, for the whole propertyCounts for more: Living areas over bedrooms and service areas; views from kitchens are highly valuedQuestion: Is the loss negligible, minor, moderate, severe or devastating?
4. ReasonableAssessed: The reasonableness of the proposal causing the impactCounts for more: A design that complies with the planning controls; where the loss comes from a breach, even a moderate impact may be unreasonableQuestion: Could a more skilful design give the same development potential and amenity with less impact on the neighbours' views?

The fourth step is where design comes in. For a complying proposal, the judgment asks whether a more skilful design could provide the same development potential and amenity and reduce the impact on the neighbours’ views; if the answer is no, the impact would probably be considered acceptable and the view sharing reasonable. That is the question height poles and photomontages help answer, because both show what a design change would and wouldn’t save.

Height poles: how a council sets them out

Willoughby City Council sets out its method in a Height Poles document dated 10 August 2011.

  • When. Height poles and joining tapes may be required where alterations or a new dwelling may affect a neighbouring property, a public space, a view corridor, a scenic protection zone or the curtilage of a heritage item, or when the council’s assessment officers ask for them. An impact can be a loss of privacy, view or light, overshadowing, or visual intrusion through a change of scale.
  • How. Timber or steel poles mark the corners, the changes in direction and the high points of the proposal, with a cross member painted bright red at the height of the proposal. Joining tapes strung between the tops trace its outline, so that from a distance the assembly shows the proposed building envelope. Each pole is labelled A, B, C and cross-referenced on the floor plans with the RL of its top.
  • When they go up. Before the application is lodged, so the impact can be tested while the design is still changing; at lodgement; or during assessment, when the council directs.
  • Certification. A registered surveyor certifies the installation and the height of the battens. Photographs of the poles taken from the affected areas may be lodged with the application to show the impact.
  • Afterwards. The poles stay until the application is determined and come down within a week. On approval, the RLs marked on the plans become the maximum approved building envelope, which a surveyor certifies when the work is finished.

Missing poles can cost an application. In 2018 the North Sydney Local Planning Panel refused a second-floor addition to a house at Kurraba Point. Its reasons included the loss of existing views from two neighbouring townhouses, and insufficient information: the council had asked for at least two height poles at the ends of the proposed central ridge, certified by a registered surveyor, and they were never provided.

3D exterior rendering of two dark-clad gabled homes with timber-lined gables and balconies above a waterfront lawn, with a jetty and two moored boats

Photomontages: the design in the real view

Height poles show an envelope: how high and how far the building reaches into the view. They don’t show the roof form, the glazing, the balustrades or the planting that decide how the building will actually sit in that view. A photomontage does: it sets the proposal, modelled from the drawings on the survey, into a photograph taken from the affected position, with the camera matched to the photographer’s.

If a photomontage goes before the Land and Environment Court as expert evidence, the Court’s policy on photomontages and visualisation tools sets the standard: the unaltered existing photograph, a plan showing where the camera stood and where it was aimed, an overlay of the proposal as a wire frame or block massing, and a method statement that names the surveyor whose survey the model came from. Our guide to the Court’s photomontage policy takes each requirement in turn, and our comparison of what six planning authorities ask renders to show covers lodgement more broadly.

Poles and photomontages should agree

A panel that has stood on a neighbour’s deck looking at the poles and tapes will compare them with the montage in the assessment report. If the two disagree, neither will be trusted. So we model the proposal from the DA drawings at the surveyed levels, the same RLs the surveyor marked on the poles, and match our camera to photographs taken where the Tenacity steps look: the neighbour’s living areas and kitchen, from a standing position, and the public places the council names. A montage taken from the spot where the poles were photographed lets the panel compare the two directly, and if the design is changed to share the view, the poles move and the montages are re-rendered together. Our photomontage service sets out what we need for each view.

3D exterior rendering of a three-level coastal home with curved white balconies, timber screens and a garden stair

A checklist before lodgement

  1. Read the council’s view sharing controls in its development control plan, and ask at pre-lodgement whether height poles will be wanted.
  2. Have a registered surveyor set and certify the poles, each labelled and cross-referenced to the plans with its RL.
  3. Photograph them from the affected rooms, living areas and kitchen first, standing, and from the public places nearby, and record where each photograph was taken.
  4. Commission photomontages from the same positions, built on the same survey, so the poles and the images show one building.
  5. Leave the poles up until the application is determined, then take them down; Willoughby asks for removal within a week.
  6. If the design changes to share the view, move the poles and update the montages together.

Sources

Each document was read in October 2026. Councils update their controls, so confirm the current requirements with your council before the poles go up.

FAQ

Questions buyers ask

What are height poles?

Temporary poles put up on a site, with tape or cable strung between their tops, that trace the height and outline of a proposed building or addition. The council, the neighbours and their consultants can then see what it would take out of a view. Willoughby City Council's method marks the height of the proposal on each pole with a cross member painted bright red.

When does a council ask for height poles?

When a proposal may affect a neighbour or the public, or when the assessing officer asks for them. Willoughby's policy lists impacts on a neighbouring property, a public space, a view corridor, a scenic protection zone or the curtilage of a heritage item, and counts loss of privacy, view or light, overshadowing and visual intrusion. Each council sets its own requirements, so read its development control plan and ask at pre-lodgement.

Do height poles have to be certified by a surveyor?

Usually, yes. Willoughby requires the installation and the height of the battens to be certified by a registered surveyor, with each pole labelled and cross-referenced to the floor plans with the RL of its top. In 2018 North Sydney's local planning panel refused an addition at Kurraba Point partly because information the council had asked for was never provided, including two height poles at the ends of the new ridge, certified by a registered surveyor.

What are the four Tenacity steps?

The planning principle from Tenacity Consulting v Warringah Council [2004] NSWLEC 140. First, the views affected: water views count for more than land views, iconic views for more than others, and whole views for more than partial ones. Second, where on the property they are seen from. Third, the extent of the impact, judged for the whole property. Fourth, whether the proposal causing it is reasonable.

Are views across a side boundary protected?

They are harder to protect. The Tenacity judgment says views across side boundaries are more difficult to protect than views from the front and rear, that sitting views are harder to protect than standing views, and that the expectation of keeping side and sitting views is often unrealistic.

Is a percentage of view loss useful?

Rarely on its own. The Tenacity judgment says a figure can be meaningless, as it would be to call a loss 20% when that 20% includes one of the sails of the Opera House, and it prefers a rating of negligible, minor, moderate, severe or devastating, made for the whole property.

Can a photomontage replace height poles?

Not by any rule we have found: the council decides what it needs to see. The two do different jobs. Poles show the envelope in the real view, to anyone standing in the neighbour's living room. A photomontage built from a known camera position shows the finished design in that same view, and if it goes before the Court it is held to the Court's photomontage policy.

What does a photomontage for a view loss assessment cost?

At Aurum Render, from $1,500 plus GST per view. Each further view from the same model costs less than the first, and views a surveyor fixes on the day, made to the Court's policy for a contested case, are quoted per project. The fixed quote sets out the views and the delivery date before work starts.

Start a project

Get a fixed quote

A fixed price, scope and delivery date within two business hours. No deposit for registered businesses.

Drawings can follow by email once we reply, or use the full quote form to add timing, budget and more detail.

We use these details only to reply to your enquiry and prepare a quote. The form also tells us how you reached us — the site that referred you, the pages you viewed and your approximate location — so we know what brings enquiries. See our privacy policy.