What are shop drawings? What a set contains, who draws it and who signs it off
Shop drawings explained: how they differ from the architect's drawings, the sheets a set contains, who prepares and reviews them, and why sets come back marked up.

A shop drawing shows how one part of a building will actually be made and put in place. The architect’s drawings say what the finished building has to be: its shape, its materials, the way it should look. A shop drawing takes one trade’s share of that, the facade panels, the joinery, the balustrades, and works out every piece: where it goes, what it is called, how big it is, how it joins its neighbours and how many of it to order.
This guide covers what a shop drawing set contains, how it differs from the drawings it is based on, who prepares and reviews it, and the reasons sets come back covered in comments. The examples come from a sample facade set we drew for a seven-storey mixed-use building.
What the film says
What are shop drawings?
A shop drawing shows how one trade’s part of a building is made and installed: every piece, its size and its place.
The architect’s drawings say what to build. Shop drawings show how the facade, joinery or steel trade will build it.
In Australia they are also called workshop drawings: drawings prepared for a fabricator to use in a workshop.
Details at 1:5 show every joint, flashing and fixing, layer by layer, from the substrate to the face.
The schedule counts every panel by type, and the cut list shows how each one comes out of a stock sheet.
The builder checks the set against the contract, then the architect reviews it against the design.
Shop drawings from $250 plus GST a sheet, with a fixed quote within two business hours.
Aurum Render: aurumrender.com.au
Design drawings and shop drawings answer different questions
The design team’s drawings, the plans, elevations, sections and details issued for construction, answer the question “what are we building?”. They are written to be accurate about intent and coordination, but they rarely say exactly where each joint falls on a façade, how a corner panel is cut or how many of each size the supplier must make.
Shop drawings answer “how will this trade build it?”. They are drawn after the trade has been chosen, with that trade’s product, its system details and its stock sizes in hand, and they are checked against the design drawings before anything is ordered. If the two disagree, the shop drawing is what changes, unless the design team accepts the difference in writing.
That is also why one building has many shop drawing sets: one for the facade, one for the windows, one for the joinery, one for the steel stairs. Each trade draws its own share, and the builder or general contractor coordinates the sets where they meet.
What a shop drawing set contains
A useful set is laid out so that a reviewer, a supplier and an installer can each find what they need without reading the whole thing. For a façade package, that usually means four kinds of sheet.
Layout elevations. Every elevation of the building, on its grid lines, with each panel or piece drawn, marked and dimensioned to the grid and the floor levels. Callouts point to the details that show how each edge and opening is closed.

Enlarged views. The places where the layout changes, such as a corner, a balcony, the podium or an unusual opening, drawn at a larger scale so the set-out of every joint can be read. A typical bay is often enlarged too, because it sets the pattern for the rest.
Details. Sections and plans through each junction: the joint at a floor line, the vertical joint, the window head and sill, the corners, the parapet, the base. Every layer from the substrate to the face is named, together with the flashings that shed water at that point and the fixings the engineer and the manufacturer have specified.

Schedules and cut lists. A count of every piece by type, with its size, taken straight from the layout, and a cut list that shows how each type comes out of the supplier’s stock sheet. A key plan shows which part of the building each sheet covers.

Around those sheets sit the title block, the sheet numbers, a revision column and general notes, including the instruction that dimensions are checked on site before anything is cut. Those notes matter: a shop drawing is drawn from documents, and the building is never exactly the documents.
A set goes out as PDF sheets for review, each with its revision in the title block, and the CAD files follow when the builder or the trade asks for them. It is drawn in the project’s own title block, sheet numbering and layer standards where the builder has them, and in the drafter’s own standard where it has none, so a reviewer finds the same information in the same place on every sheet.
Who prepares them, and who reviews them
The trade installing the work is responsible for its shop drawings. Many trades draw their own; many others pass the work to a drafting studio, because a facade subcontractor’s best people are needed on site, not at a desk.
The finished set goes to the builder or general contractor, who checks it against the contract: the right product, the right scope, nothing that clashes with another trade. It then goes to the architect, and where relevant to the engineer or another consultant, for review against the design. The set comes back with a stamp or a response saying whether the work can proceed, proceed with the noted corrections, or must be revised and submitted again.
A reviewer’s approval does not move responsibility for accuracy. The design team checks that the set follows the design; the trade remains responsible for its dimensions and quantities and for building what the set shows. Where a part of the work needs engineering, such as the brackets that carry a facade or a balustrade’s fixings, a qualified engineer designs it, and the shop drawings show that design. A drafter, ourselves included, draws it but does not certify it.
Shop drawings or workshop drawings: how Australia defines and draws them
Australian specifications and builders use both names, and the definition explains the second one. The Australian Institute of Architects' Acumen practice note on shop drawings quotes Standards Australia: they are drawings prepared for a fabricator to use in a workshop. The note keeps them apart from the drawings a contractor provides as part of a design and construct process, and says that in some cases the specification requires the contractor to submit shop drawings for review, so whether a set reaches the architect depends on the job.
Apartment buildings in New South Wales add a rule of their own. Class 2 buildings come under the Design and Building Practitioners Act, and the NSW Government's guidance says the designs lodged for regulated work must be construction issued regulated designs, not shop drawings or other drafts. The facade or joinery set is therefore drawn to the lodged design, and where it would vary a building element, a new regulated design has to be prepared before the varied work goes ahead. Our guide to shop drawings on Class 2 apartment buildings walks through the order.
Where a builder has no drawing standard of its own, the Australian reference is AS 1100.101, Standards Australia's general principles of technical drawing. It covers the sizes and layout of drawing sheets, the types and thicknesses of lines, lettering, scales, sectioning and dimensioning: the conventions an Australian reviewer expects to read a set by.
Sources, checked November 2026: Australian Institute of Architects, Acumen: Shop drawings (published 18 January 2023); NSW Government, Design practitioner obligations; Standards Australia, AS 1100.101: Technical drawing, Part 101: General principles.
Why sets come back marked up
Most returned sets fail for a handful of reasons, and nearly all of them can be caught before the first issue.
- A difference from the design that isn’t flagged. The trade substitutes a different board, moves a joint or changes a flashing, and the drawing simply shows the new version. Reviewers look for exactly that. Any departure should be clouded and listed so it can be accepted on purpose.
- Missing junctions. The typical details are drawn, but not the corner at the balcony or the meeting with the shopfront glazing. The places where two systems meet are where reviewers look first.
- Counts that don’t match the layout. A schedule typed by hand drifts from the elevations after the first revision. A schedule taken from the same model as the layout stays in step.
- Dimensions nobody can check. A layout dimensioned only between panels, with no ties to grid lines and floor levels, cannot be compared with the architect’s drawings.
- Revisions without a record. A resubmitted set with changes that are not clouded, or comments without a response, means the reviewer has to start again from the beginning.
How long shop drawings take
It depends on the building and on the documents. A facade with four plain elevations and one panel type is a short job; a mixed-use building whose layout changes at every balcony and podium, with a dozen special junctions, is not. The completeness of the architectural set matters as much as its size: every question that has to go back to the architect adds days before the first issue.
Plan the shop drawings backwards from the date materials must be ordered. Allow for the drafting, the builder’s check, the design team’s review and at least one round of revisions, because the first issue is rarely the last, and treat the review period named in the contract as the minimum, not the forecast.
Where to go from here
If you are about to commission a set, send the drafter the architectural set, the specification section for the system and the manufacturer’s details together. Those three documents decide most of the questions above. Our shop drawings page describes how we draw a package and what we need to quote it.