On an apartment building in New South Wales, the facade is designed twice. First by the design team, as a regulated design that a registered design practitioner declares and the builder lodges before the work starts. Then by the trade that will build it, as shop drawings that turn that design into marked panels, drawn junctions and an order for material. The two documents do different jobs, and the rules that sit around Class 2 buildings treat them differently.

This guide sets out where shop drawings fit on a Class 2 job in NSW: what has to exist before they are drawn, what happens when they propose a change, the facade detail the regulated design should already contain, and the NCC checks a shop drawing set should make easy. The illustrations come from a sample facade set we drew for a seven-storey mixed-use apartment building.

The design comes first, and it is not a shop drawing

The Design and Building Practitioners Act applies to regulated buildings, which the NSW Government lists as currently Class 2, 3 or 9c buildings, including mixed-use buildings. For building work on those buildings that involves a building element or a performance solution, a registered design practitioner prepares the regulated design and gives a design compliance declaration for it.

The guidance is plain about what qualifies. The designs must be construction issued regulated designs, not shop drawings or other drafts. They are lodged on the NSW Planning Portal by the building practitioner, or an appointed appropriate practitioner, and they must be lodged before any building work relevant to them can start. A certifier cannot issue a construction certificate or a complying development certificate for regulated work without declared designs.

So the order on a Class 2 facade is fixed: regulated design, declaration, lodgement, then shop drawings drawn to that design. A shop drawing can show how the design will be built in far more detail than the design shows. It cannot stand in for it.

When a shop drawing proposes a change

Shop drawings often propose changes: a different panel product, a joint moved to suit a stock sheet, another manufacturer’s flashing. Under the NSW scheme, how such a change is handled depends on what it touches.

If it varies a building element or a performance solution, it is a variation. The NSW Government’s guidance says new regulated designs must be prepared before the varied building work can continue, that updated or new designs are lodged on the Portal, and that each varied design and declaration is lodged within one day of the variation. That is the design practitioner’s work, not the drafter’s and not the site’s.

What a shop drawing set can do is make such a change impossible to miss. Every departure from the declared design is clouded on the sheet and listed in the transmittal, so the builder and the design practitioner see it before anything is ordered, rather than discovering it on the scaffold.

Sample shop drawing sheet SD-601: panel schedule for the north elevation with sizes, quantities and areas, a cut list from 1,200 by 3,000 mm stock sheets and a key plan

What the regulated facade design should already show

The Regulated Design Guidance Material, approved under the Design and Building Practitioners Regulation 2021, sets out the minimum content of a regulated design, and it has a section on facades. Among other things:

  • Elevations must include the project’s geographical orientation, and should include a small block plan cross-referencing where each elevation sits on the plan.
  • 1:5 details for weatherproofing cover the interfaces between façade types and between the facade and the structure, the joint design, the facade and balcony junction, the facade and podium junction, and the parapet junction with the roof.
  • Weatherproofing must say whether the facade is a pressure-equalised or a face-sealed system and account for the junctions between systems.

That list is useful to a shop drawing team in two ways. It tells them which junctions the design practitioner has already resolved, so the shop details can follow them rather than reinvent them. And it gives the shop drawing set a natural structure: each elevation keyed to a plan, and each junction the guidance names drawn at a scale where every layer can be read.

Sample shop drawing sheet SD-501: four typical facade details at 1:5, the horizontal joint at the floor line, the vertical joint, the window head and the window sill of a fibre cement panel system on top-hat battens

Non-combustible means every layer

The second check a facade set has to survive is material. Under the National Construction Code’s Deemed-to-Satisfy Provisions, in a building required to be of Type A or B construction, external walls and their components must be non-combustible, including the facade covering, framing and insulation. In NCC 2022 that is clause C2D10. States adopt new editions of the NCC on their own timetables, so confirm which edition applies to your job.

The risk on a shop drawing is substitution. A different backing board, a membrane from another supplier or a change of insulation can each move a wall outside the declared design, and a layout drawing that shows only the outer panel hides it. Details that name every layer from the substrate out, as specified, make the check quick for the builder, the design practitioner and the certifier alike.

A short checklist for the builder and the trade

Before the first shop drawing issue on a Class 2 job:

  1. Get the lodged regulated designs, not an earlier revision, and draw to them.
  2. List the questions the shop drawing team finds where the design is silent or inconsistent, and send them to the design practitioner before drawing around them.
  3. Name every layer in every junction detail, as specified, with the product it is.
  4. Cloud and list every departure from the declared design, including substitutions the supplier suggests.
  5. Key each elevation to a plan and number the details so they can be read against the regulated design sheet by sheet.
  6. Keep the counts in the model, so a revision to one sheet updates the schedule and the cut list with it.
Sample shop drawing sheet SD-301: enlarged elevation of one bay over levels 2 to 4 at 1:50, with panel setting-out in millimetres, floor levels and callouts to the joint, head and sill details

Our shop drawings page explains how we draw facade and joinery packages for apartment, mixed-use and commercial buildings. For the basics of a set, read what shop drawings are.

Where these rules come from

The lodgement, variation and certifier rules above are from the NSW Government's page on design practitioner obligations, last updated 8 September 2026. The facade detail expected of a regulated design is from the Regulated Design Guidance Material, approved under clause 9(1)(c) of the Design and Building Practitioners Regulation 2021. The non-combustibility rule is clause C2D10 of NCC 2022 Volume One.

Sources, checked 15 November 2026: NSW Government, Design practitioner obligations when working on regulated buildings; NSW Government, Regulated Design Guidance Material; ABCB, NCC 2022 Volume One, Part C2.

FAQ

Questions buyers ask

Can shop drawings be lodged as the regulated design for a facade?

No. Only construction issued regulated designs, prepared and declared by a registered design practitioner, can be lodged for regulated work, and the NSW guidance names shop drawings and other drafts as not qualifying. The shop drawings are drawn to the lodged facade design afterwards.

What happens if the facade subcontractor wants to change the system?

If the change varies a building element or a performance solution, it is a variation under the regulated design scheme. New regulated designs must be prepared before the varied work can continue, and each varied design and declaration is lodged on the NSW Planning Portal. Draw the proposal on the shop drawings, flag it clearly, and let the design practitioner decide.

Does the regulated design scheme apply to mixed-use buildings?

Yes. The NSW Government lists the regulated building classes as currently Class 2, 3 or 9c, including mixed-use buildings, so a building with shops below and apartments above is covered.

Do shop drawings need to show which materials are non-combustible?

They should name every layer as specified, so whoever checks the set can confirm it matches the declared design. On a building required to be of Type A or B construction, the NCC's Deemed-to-Satisfy Provisions require the external walls, including the facade covering, framing and insulation, to be non-combustible, so a substituted board, membrane or insulation is the change most worth flagging.

Start a project

Get a fixed quote

A fixed price, scope and delivery date within two business hours. No deposit for registered businesses.

Drawings can follow by email once we reply, or use the full quote form to add timing, budget and more detail.

We use these details only to reply to your enquiry and prepare a quote. The form also tells us how you reached us — the site that referred you, the pages you viewed and your approximate location — so we know what brings enquiries. See our privacy policy.